Resolving a 7 year recurring pump failure

power generation site
Customer India Power Major
Location Central Eastern India 
Industry Power Generation
Key Services

PUMPS RETROFITTED


1
WITH 8 IN PROGRESS

MTBF FROM


4 to 18 months

TURNKEY DELIVERY WITHIN


6 months

PARTS RE-ENGINEERED


50++

THE IMPACT


Peace of mind with regained reliability for critical application via re-engineering solution with minimal physical and carbon impact

The Challenge

7 years of immense disruption due to failing pumps

Condensate extraction pumps (CEPs) at one of the company’s power stations in central eastern India were failing at an unusual rate.

  • Every pump was failing within four months of scheduled maintenance. Some were even failing after no more than 25 days of scheduled maintenance.
  • The plant had been grappling with these issues for nearly seven years, the OEM was unable to suggest any changes that would help the pumps last longer.
  • The failures took two forms:
    - Catastrophic shaft failures at the muff-coupling section of the pump, either on the torsional plane or due to crushing
    - Leakage through a bottom column weld joint.
  • An OEM report concluded that the shaft had failed as a result of weld buildup.
  • But the sample that had been tested at the lab by the OEM had been from a shaft which had failed previously and undergone urgent repairs. The OEM hadn’t tested any of the brand-new pumps with no weld buildup – even though these pumps were also failing.
  • Report didn’t accurately account for the real conditions on site at the power plant, explain why brand-new pumps were continually failing and didn’t address the leakage through the bottom column weld joint.
  • It was clear that the solution to this conundrum wouldn’t be found by examining the pumps in isolation. They needed an expert assessment of their entire setup.
  • They called us in to help.

The Solution

Uncovering the cause – and building the perfect solution

We conducted investigations to find out:

  • Were they operating under the conditions for which they were designed?
  • Were they being used within their preferred operating range?
  • If the correct materials had been used. Was there a mismatch between the material of the pump and the material of the shaft?
  • If the shaft geometry, coupling, key sizing, and column pipe wall thickness had been designed according to best practices.

During this process, we uncovered a few important weaknesses.

  • Uneven stress distribution on the key along with uneven distribution of bending and crushing forces on key and shaft caused failures.
  • Thin column wall thickness was lower than required while bottom column was missing additional stiffeners.
  • This resulted in bottom column weld joints withstanding increased stress and would crack over time, which in turn caused.
  • Below-grade structural vibration.
  • Misalignment of bearing spiders during operation.
  • Eventual pump seizure.
  • Original design of bearing spiders follow best engineering practice.
  • The alignment of the line bearing would largely depend on assembly skills and would risk damage to the sealing O-rings.

Our team designed and began implementing the following modifications to the pumps:

  • A new shaft design with a closed-end keyway and a split ring with a wider diameter.
  • Changing the MOC of the shaft from 1.4313.09 to 17-4 PH steel to improve the safety margins of the pump.
  • A new muff-coupling design with a large split-shoulder ring and two separate keys, removing the need for one key to pass between different shafts.
  • Increasing the wall thickness of column pipes and adding additional stiffeners on the bottom column pipe to prevent leakage.
  • Adding a centralizer feature to make it easier for the team to assemble the pump and dismantle it from the barrel.
  • A new bearing spider design to seal the column and ensure the line bearing remained aligned.
  • A new design for a line shaft bearing and sleeves

All the above were done on existing pumps, negating CAPEX with high capital outlay

 

Explore our solutions

  • Any pump, Anywhere: OEM-X Line
    As a market-leading manufacturer of precision pump equipment, we also offer 24/7 technical support for all other makes, all over the world.

  • Pump retrofit solutions
    Our pump retrofit solutions provide a faster, smarter way to restore and enhance performance—helping plants reduce costs with minimal disruption.

The Customer Benefit

Transformative reliability at fractional cost of new CAPEX

  • The new pumps will have a minimum one-year warranty, an improvement with significant impact on the productivity and costs of the power station.
  • By November 2022, the MTBF had already increased from 4 to 11 months.
  • To date, the pump’s operating parameters – including vibration and bearing temperature – remain well within limits.
  • At the time of writing, the modified pump has been running for more than 18 months without a single failure, an impressive improvement on the original MTBF of four months.
Contact us